Week 36 (Feb 22-29, 2024)
Construction of Jolley School, School

Week 36 (Feb 22-29, 2024)

Review of work for the week:
-Transported 4200 lbs of rebar from Leogane to Tavet, 100% of goal complete.
-Transported 200 cement bags from Petit Goâve to Tavet, 80% complete.
-Steel reinforcement for intermediary chain beam, Block 4 (Classrooms), 0% complete.
-Formwork for intermediate chain beam, Block 4 (Classrooms), 0% complete.
-Concrete pouring for intermediary chain beam, Block 4 (Classrooms), 0% complete.
-The planned activities at buildings 4 and 5, i.e., tasks 3, 4, 5, were not carried out for this week, following a decision by the technical team to concentrate their resources to finalize the structural work for Block 3 (Classroom).
-Laying 15cm Block wall panel, Block 3 (Classrooms), 80% complete.
-Steel reinforcement for window frame, Block 3 (Classrooms), 100% complete.
- Formwork including steel reinforcement for window frame, Block 3 (Classrooms), 100% complete.
-Concrete pouring for window frames, Block 3 (Classrooms), 100% complete.
-Steel reinforcement for doors frame, Block 3 (Classrooms), 33% complete.
- Formwork reinforcement for doors frame, Block 3 (Classrooms), 33% complete.

+1 (801) 830-3043

mail@haitihealthinitiative.org

Haiti Health Initiative aims to improve the overall health and well being of rural Haitians, one community at a time. We seek to accomplish this through providing education and services in primary health care, dental care, public health, and nutrition within each community at risk.

If you have questions about Haiti Health Initiative, contact

Marc-Aurel Martial at 

mmartial@haitihealthinitiative.org 

or at 801-830-3043.

© All Copyrights 2024 by Haiti Health Initiative