Week 44 (April 17-24, 2024) Building the Jolley School, Timo Haiti
Construction of Jolley School, School
Week 44 (April 17-24, 2024)
Below is a summary of activities completed during the previous period.
-Laying cement blocks for partition walls, Block 5 (Kitchen/Cafeteria), 100% complete
-Formwork for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete
-Concrete pouring for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete.
-Concrete pouring for front door threshold, Block 1 (Administration) & Block 2 (Library/Computer Room), 100% complete
-Formwork doors, Block 1 (Administration) & Block 2 (Library/Computer Room), 100% complete
-Concrete pouring for doors, Block 1 (Administration) & Block 2 (Library/Computer Room), 100% complete
Percentage général des travaux exécutés |Overall percentage of work completed
52.00%
Previous period: 50%

+1 (801) 830-3043

mail@haitihealthinitiative.org

Haiti Health Initiative aims to improve the overall health and well being of rural Haitians, one community at a time. We seek to accomplish this through providing education and services in primary health care, dental care, public health, and nutrition within each community at risk.

If you have questions about Haiti Health Initiative, contact

Marc-Aurel Martial at 

mmartial@haitihealthinitiative.org 

or at 801-830-3043.

© All Copyrights 2024 by Haiti Health Initiative