WEEK 52 (June 12-19, 2024) – Building the Jolley School, Timo Haiti
School

WEEK 52 (June 12-19, 2024)

Below is a summary of activities completed during the previous period.

a) Aluzinc sheet metalinstallation, block 1(Administration): This activity is completed at 5 % during this week.

b) laying laths (metalroofing), block 1 (Administration): This activity is completed at 100 % during this week.

c) laying laths (metalroofing) , block 2 (Library/ Computer) : This activity is completed at 100 % during this week.

d) laying laths (metalroofing), block 3 (Clasrooms 1-3): This activity is completed at 100 % during this week.

e) Welding metal roofs, block 1 (Administration) : This activity is completed at 100% during this week.

f) Welding metal roofs, block 3 (Classrooms 1); his activity is completed at 100% during this week.

g) Steel reinforcementfor top chain beam, block 4(Classrooms 4-6) : This activity is completed at 100% during this week.

h) Formwork for top chainbeam, Block 4 (Classrooms 4-6): This activity is completed at 100% during this week

i) Pouring concrete for top chain beam, Block 4 (Classrooms 4-6): This activity is completed at 100% during this week

j) Steel structure for roofing, Block 4 (Classrooms 4-6), (25%): This activity is completed at 25 % during this week.

+1 (801) 830-3043

mail@haitihealthinitiative.org

Haiti Health Initiative aims to improve the overall health and well being of rural Haitians, one community at a time. We seek to accomplish this through providing education and services in primary health care, dental care, public health, and nutrition within each community at risk.

If you have questions about Haiti Health Initiative, contact

Marc-Aurel Martial at 

mmartial@haitihealthinitiative.org 

or at 801-830-3043.

© All Copyrights 2024 by Haiti Health Initiative