Week 46 Update (May 1-8, 2024) Building the Jolley School, Timo Haiti
Construction of Jolley School, School
'}}

Week 46 Update - May 1-8, 2024

Below is a summary of activities completed during the previous period.
1. Formwork steel columns, Block 1 (Administration) & Block 2 (Library/ Computer), 100% complete
2. Concrete pouring over steel columns, Block 1 (Administration) & Block 2 (Library/ computer), 100% complete
3. Concrete pouring over steel columns, Block 3 (Classrooms 1-3), 100% complete
4. Formwork steel columns, Block 4 (Classrooms 4-6), 25% complete
5. Formwork steel columns, Block 5 (Kitchen/Cafeteria), 25% complete
6. Concrete pouring over steel columns, Block 5, 25% complete