Update: Steel reinforcement parquet floor, block 4 (Classrooms 4-6),100%. Electrical flooring, block 4(Classrooms 4-6), 100%. concrete pouring parquet floor, block 3(Classrooms 1-3), 100%. Floating, block 3(Classrooms 1-3), 100%. Concrete pouring parquet floor, block 3(Classrooms 1-3), 100%. Plug sealing, block 4(Classrooms 4-6) ,100%. Purchase and transport of 300 bags of cement (100%). Facade préparation (100%).
Month: August 2024
Week 61 (Aug 14-Aug 21, 2024) – Building of the Jolley School
Review of activities from the previous period : Transportation of doors, 19 units 100%. Transportation of windows, 100%. 21 units Steel reinforcement parquet floor, block 3 (Classrooms 1-3) ,100%. Electrical flooring, block 3(Classrooms 1-3), 100%. Concrete pouring parquet floor, block 3(Classrooms 1-3), 70%. Plug sealing, block 1(Administration) ,100%. Plug sealing, block 2(Library / Computer) ,100%.… Continue reading Week 61 (Aug 14-Aug 21, 2024) – Building of the Jolley School
Graduation of the 1st Tiling class
Graduation of the 1st Tiling class last week. The classes were taught by Dieudoit at the community center. It is neat to see how that really went all out to make it a special occasion!
Week 60 (Aug 7-Aug 14) – Building of the Jolley School
Recap: concrete pouring parquet floor, block 1(Administration), 100%. concrete pouring parquet floor, block 2(Library / Computer), 100%. Aluzinc sheet metal installation, block 5,100 %. Floating, block 3 (Classrooms 1-3), 100 %. Floating, block 4 (Classrooms 4-6), 100%. Aluzinc sheet metal installation, main corridor, blocks 3(Classrooms 1-3) and 4(Classrooms 4-6), 100%. Transportation of windows for blocks… Continue reading Week 60 (Aug 7-Aug 14) – Building of the Jolley School
School progress and Pulley system revisions – Building the Jolley School, Timo Haiti
Lots of work on the school! Plus working on the pulley system for the transportation of materials to the school site.
Week 59 (July 31-Aug 7, 2024) Building of the Jolley School
Review of activities: Steel framing, block 1 (Administration), 100%. Steel framing, block 2 (Library / Computer), 100%. Electrical installation, block 1 (Administration) ,100%. Electrical installation, block 2 (Library / Computer) ,100%. Floating, block 1 (Administration), 95%. Floating, block 2 (Library / Computer), 95%. Floating, block 3 (Classrooms 1-3), 100%. Steel structure for roofing, block 5(Cafeteria),… Continue reading Week 59 (July 31-Aug 7, 2024) Building of the Jolley School