WEEK 52 (June 12-19, 2024) – Building the Jolley School, Timo Haiti

WEEK 52 (June 12-19, 2024) Below is a summary of activities completed during the previous period. a) Aluzinc sheet metalinstallation, block 1(Administration): This activity is completed at 5 % during this week. b) laying laths (metalroofing), block 1 (Administration): This activity is completed at 100 % during this week. c) laying laths (metalroofing) , block… Continue reading WEEK 52 (June 12-19, 2024) – Building the Jolley School, Timo Haiti

WEEK 51 (June 5-12, 2024) – Building the Jolley School, Timo Haiti

WEEK 52 (June 12-19) Below is a summary of activities completed during the previous period. a) Aluzinc sheet metalinstallation, block 1(Administration): This activity is completed at 5 % during this week. b) laying laths (metalroofing), block 1 (Administration): This activity is completed at 100 % during this week. c) laying laths (metalroofing) , block 2… Continue reading WEEK 51 (June 5-12, 2024) – Building the Jolley School, Timo Haiti

WEEK 50 (May 29-June 5, 2024) – Building the Jolley School, Timo Haiti

WEEK 50 (May 29-June 5, 2024) The skilled workers are not native to Timo but are provided with temporary accommodation in the Timo community during the construction project. The skilled workers include carpenters who build formwork; ironworkers who install steel reinforcement; and masons who pour concrete. The day laborers, natives of Timo, assist the skilled… Continue reading WEEK 50 (May 29-June 5, 2024) – Building the Jolley School, Timo Haiti