WEEK 52 (June 12-19, 2024) – Building the Jolley School, Timo Haiti

WEEK 52 (June 12-19, 2024) Below is a summary of activities completed during the previous period. a) Aluzinc sheet metalinstallation, block 1(Administration): This activity is completed at 5 % during this week. b) laying laths (metalroofing), block 1 (Administration): This activity is completed at 100 % during this week. c) laying laths (metalroofing) , block… Continue reading WEEK 52 (June 12-19, 2024) – Building the Jolley School, Timo Haiti

WEEK 51 (June 5-12, 2024) – Building the Jolley School, Timo Haiti

WEEK 52 (June 12-19) Below is a summary of activities completed during the previous period. a) Aluzinc sheet metalinstallation, block 1(Administration): This activity is completed at 5 % during this week. b) laying laths (metalroofing), block 1 (Administration): This activity is completed at 100 % during this week. c) laying laths (metalroofing) , block 2… Continue reading WEEK 51 (June 5-12, 2024) – Building the Jolley School, Timo Haiti

WEEK 50 (May 29-June 5, 2024) – Building the Jolley School, Timo Haiti

WEEK 50 (May 29-June 5, 2024) The skilled workers are not native to Timo but are provided with temporary accommodation in the Timo community during the construction project. The skilled workers include carpenters who build formwork; ironworkers who install steel reinforcement; and masons who pour concrete. The day laborers, natives of Timo, assist the skilled… Continue reading WEEK 50 (May 29-June 5, 2024) – Building the Jolley School, Timo Haiti

Week 49 (May 22-29, 2024) – Building of Jolley school Timo, Haiti

WEEK 49 (May 22-29, 2024) Below is a summary of activities completed during the previous period: 1) Steel reinforcement for top chain beam, Block 3 ; activity is completed at 70% during this week. 2) Formwork for top chain beam, Block 3 (Classrooms 1-3) : this activity is completed at 20 % during this week… Continue reading Week 49 (May 22-29, 2024) – Building of Jolley school Timo, Haiti

Week 48 (May 15-23, 2024) – Building the Jolley School, Timo Haiti

Week 48 – May 15-23, 2024 Below is a summary of activities from the previous period: 1) Steel reinforcement for top chain beam, Block 1 (Administration), 100% complete 2) Steel reinforcement for top chain beam, Block 2 (Library /Computer Room), 75% complete 3) Formwork for top chain beam, Block 1(Administration), 0% complete 4) Steel roof… Continue reading Week 48 (May 15-23, 2024) – Building the Jolley School, Timo Haiti

Week 47 (May 8-15, 2024) Building the Jolley School, Timo Haiti

Week 47 (May 8-15, 2024) HIGHLIGHT: we are at the end of STEP 4 (Step 4 Vertical Wall Erection: Concrete Block and Masonry) of the Calendar of Activities agreed upon on May 18, 2024 UPDATES: -Steel reinforcement for top chain beam, Block 1 (Administration), 60% complete -Steel reinforcement for top chain beam, Block 2 (Library… Continue reading Week 47 (May 8-15, 2024) Building the Jolley School, Timo Haiti

Week 46 Update (May 1-8, 2024) Building the Jolley School, Timo Haiti

Week 46 Update – May 1-8, 2024 Below is a summary of activities completed during the previous period. 1. Formwork steel columns, Block 1 (Administration) & Block 2 (Library/ Computer), 100% complete 2. Concrete pouring over steel columns, Block 1 (Administration) & Block 2 (Library/ computer), 100% complete 3. Concrete pouring over steel columns, Block… Continue reading Week 46 Update (May 1-8, 2024) Building the Jolley School, Timo Haiti

Week 44 (April 17-24, 2024) Building the Jolley School, Timo Haiti

Week 44 (April 17-24, 2024) Below is a summary of activities completed during the previous period. -Laying cement blocks for partition walls, Block 5 (Kitchen/Cafeteria), 100% complete -Formwork for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete -Concrete pouring for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete. -Concrete pouring for front door threshold, Block… Continue reading Week 44 (April 17-24, 2024) Building the Jolley School, Timo Haiti