Week 36 (Feb 22-29, 2024) Review of work for the week: -Transported 4200 lbs of rebar from Leogane to Tavet, 100% of goal complete. -Transported 200 cement bags from Petit Goâve to Tavet, 80% complete. -Steel reinforcement for intermediary chain beam, Block 4 (Classrooms), 0% complete. -Formwork for intermediate chain beam, Block 4 (Classrooms), 0%… Continue reading Week 36 (Feb 22-29, 2024)
Month: February 2024
Week 35 – (Feb 9-15, 2024) – Building of the Jolley School
Week 35 – (Feb 9-15, 2024) RECAP: The project has consistently advanced each week, thanks to the leadership of the wise and experienced Haitian contractor. He has adjusted strategies multiple times to address project requirements and resolve emerging challenges. Nevertheless, the project has encountered significant delays due to persistent obstacles, including the prevailing security concerns… Continue reading Week 35 – (Feb 9-15, 2024) – Building of the Jolley School