Week 49 (May 22-29, 2024) – Building of Jolley school Timo, Haiti

WEEK 49 (May 22-29, 2024) Below is a summary of activities completed during the previous period: 1) Steel reinforcement for top chain beam, Block 3 ; activity is completed at 70% during this week. 2) Formwork for top chain beam, Block 3 (Classrooms 1-3) : this activity is completed at 20 % during this week… Continue reading Week 49 (May 22-29, 2024) – Building of Jolley school Timo, Haiti

Week 48 (May 15-23, 2024) – Building the Jolley School, Timo Haiti

Week 48 – May 15-23, 2024 Below is a summary of activities from the previous period: 1) Steel reinforcement for top chain beam, Block 1 (Administration), 100% complete 2) Steel reinforcement for top chain beam, Block 2 (Library /Computer Room), 75% complete 3) Formwork for top chain beam, Block 1(Administration), 0% complete 4) Steel roof… Continue reading Week 48 (May 15-23, 2024) – Building the Jolley School, Timo Haiti

Week 47 (May 8-15, 2024) Building the Jolley School, Timo Haiti

Week 47 (May 8-15, 2024) HIGHLIGHT: we are at the end of STEP 4 (Step 4 Vertical Wall Erection: Concrete Block and Masonry) of the Calendar of Activities agreed upon on May 18, 2024 UPDATES: -Steel reinforcement for top chain beam, Block 1 (Administration), 60% complete -Steel reinforcement for top chain beam, Block 2 (Library… Continue reading Week 47 (May 8-15, 2024) Building the Jolley School, Timo Haiti

Week 46 Update (May 1-8, 2024) Building the Jolley School, Timo Haiti

Week 46 Update – May 1-8, 2024 Below is a summary of activities completed during the previous period. 1. Formwork steel columns, Block 1 (Administration) & Block 2 (Library/ Computer), 100% complete 2. Concrete pouring over steel columns, Block 1 (Administration) & Block 2 (Library/ computer), 100% complete 3. Concrete pouring over steel columns, Block… Continue reading Week 46 Update (May 1-8, 2024) Building the Jolley School, Timo Haiti