Week 58 (July 24-July 31, 2024) – Building of the Jolley School

Update: Aluzinc sheet metal installation main ridge, 70%. Aluzinc sheet metal installation, block 1(Administration), 100%. Aluzinc sheet metal installation, block 2(Library / Computer), 70%. Aluzinc sheet metal installation, block 3(Classrooms 1-3), 100%. Aluzinc sheet metal installation, block 4(Classrooms 4-6), 70%. Floating, block 1 (Administration), 90%. Floating, block 2 (Library / Computer), 80%. Plastering chain beam,… Continue reading Week 58 (July 24-July 31, 2024) – Building of the Jolley School

WEEK 51 (June 5-12, 2024) – Building the Jolley School, Timo Haiti

WEEK 52 (June 12-19) Below is a summary of activities completed during the previous period. a) Aluzinc sheet metalinstallation, block 1(Administration): This activity is completed at 5 % during this week. b) laying laths (metalroofing), block 1 (Administration): This activity is completed at 100 % during this week. c) laying laths (metalroofing) , block 2… Continue reading WEEK 51 (June 5-12, 2024) – Building the Jolley School, Timo Haiti

Week 47 (May 8-15, 2024) Building the Jolley School, Timo Haiti

Week 47 (May 8-15, 2024) HIGHLIGHT: we are at the end of STEP 4 (Step 4 Vertical Wall Erection: Concrete Block and Masonry) of the Calendar of Activities agreed upon on May 18, 2024 UPDATES: -Steel reinforcement for top chain beam, Block 1 (Administration), 60% complete -Steel reinforcement for top chain beam, Block 2 (Library… Continue reading Week 47 (May 8-15, 2024) Building the Jolley School, Timo Haiti

Week 46 Update (May 1-8, 2024) Building the Jolley School, Timo Haiti

Week 46 Update – May 1-8, 2024 Below is a summary of activities completed during the previous period. 1. Formwork steel columns, Block 1 (Administration) & Block 2 (Library/ Computer), 100% complete 2. Concrete pouring over steel columns, Block 1 (Administration) & Block 2 (Library/ computer), 100% complete 3. Concrete pouring over steel columns, Block… Continue reading Week 46 Update (May 1-8, 2024) Building the Jolley School, Timo Haiti

Week 44 (April 17-24, 2024) Building the Jolley School, Timo Haiti

Week 44 (April 17-24, 2024) Below is a summary of activities completed during the previous period. -Laying cement blocks for partition walls, Block 5 (Kitchen/Cafeteria), 100% complete -Formwork for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete -Concrete pouring for doors and windows, Block 5 (Kitchen/Cafeteria), 100% complete. -Concrete pouring for front door threshold, Block… Continue reading Week 44 (April 17-24, 2024) Building the Jolley School, Timo Haiti

Week 43 (April 10-17, 2024) — Building the Jolley School, Timo Haiti

Week 43 (April 10-17, 2024) Progress made: -Transported steel rebar for roofing to the site 111 rebar 2×4, and 123 rebar 2×2, 20% complete -Preparation of the top chain beam, Block 1 (Administration), 0% complete -lmplantation of a green space in the main corridor between Block 3 (Classrooms 1-3) and Block 4 (Classrooms 4-6), 0%… Continue reading Week 43 (April 10-17, 2024) — Building the Jolley School, Timo Haiti

Week 42 (April 3-10, 2024) — Building the Jolley School, Timo Haiti

Week 42 (April 3-10, 2024) Recap: -We are still at STEP 4 (Step 4 Vertical Wall Erection: Concrete Block and Masonry) of the Calendar of Activities agreed upon on May 18, 2023. Below is a summary of activities completed during the previous period. -Steel reinforcement of door and window lintels, Block 1 (Administration) & Block… Continue reading Week 42 (April 3-10, 2024) — Building the Jolley School, Timo Haiti

Week 41 (March 28-April 4, 2024) — Building the Jolley School, Timo Haiti

Week 41 (March 28-April 4, 2024) Progress: -We are still at STEP 4 (Step 4 Vertical Wall Erection: Concrete Block and Masonry) of the Calendar of Activities agreed upon on May 18, 2023. -Below is a summary of activities completed during the previous period. -Steel columns installation, Block 5 (Kitchen/Cafeteria), 100% complete. -Laying cement blocks… Continue reading Week 41 (March 28-April 4, 2024) — Building the Jolley School, Timo Haiti

Week 40 (March 22-27, 2024) — Building the Jolley School, Timo Haiti

Week 40 (March 22-27, 2024) Recap: We are at STEP 4 (Step 4 Vertical Wall Erection: Concrete Block and Masonry) of the Calendar of Activities agreed upon on May 18, 2023. Below is a summary of activities completed during the previous period. 1. Laying cement blocks, Block 4 (Classrooms 4-6), 100% complete 2. Steel columns… Continue reading Week 40 (March 22-27, 2024) — Building the Jolley School, Timo Haiti